This is default featured post 1 title
Go to Blogger edit html and find these sentences.Now replace these sentences with your own descriptions.This theme is Bloggerized by Lasantha Bandara - Premiumbloggertemplates.com.
This is default featured post 2 title
Go to Blogger edit html and find these sentences.Now replace these sentences with your own descriptions.This theme is Bloggerized by Lasantha Bandara - Premiumbloggertemplates.com.
This is default featured post 3 title
Go to Blogger edit html and find these sentences.Now replace these sentences with your own descriptions.This theme is Bloggerized by Lasantha Bandara - Premiumbloggertemplates.com.
This is default featured post 4 title
Go to Blogger edit html and find these sentences.Now replace these sentences with your own descriptions.This theme is Bloggerized by Lasantha Bandara - Premiumbloggertemplates.com.
This is default featured post 5 title
Go to Blogger edit html and find these sentences.Now replace these sentences with your own descriptions.This theme is Bloggerized by Lasantha Bandara - Premiumbloggertemplates.com.
Minggu, 19 Februari 2012
CAT DINDING BINTIK-BINTIK
PENYABUNAN
LAHAN MIRING
RAB
Gambar 44.1 Tabel analisa harga satuan pekerjaan pasangan dinding bata campuran 1:3
Pembaca sekalian, setelah mengetahui cara memilih bata dan metode pelaksanaanya maka tiba saatnya kita mengetahui berapa uang yang harus dikeluarkan untuk membikin pasangan dinding bata atau pasangan dinding bata merah. Nah langkah pertamanya adalah anda lihat table di atas (Gambar 44.1 dan Gambar 44.2)
PASANGAN BATA 1:3 (1 PASIR : 3 SEMEN)
| ||
Uraian
|
Produktifitas dalam 1 hari kerja
| |
Pekerja
|
1,4667
|
m2
|
Tukang bata
|
4,4014
|
m2
|
PASANGAN BATA 1:5 (1 PASIR : 5 SEMEN)
| ||
Uraian
|
Produktifitas dalam 1 hari kerja
| |
Pekerja
|
2,4450
|
m2
|
Tukang bata
|
7,3335
|
m2
|
PASANGAN DINDING BATA
Faktor terpenting pada pekerjaan tahan ini meliputi 2 hal :
- Detail kontruksi pada bagian pertemuan antara kolom dengan dinding (lihat pada posting sebelumnya)
- Detail pelaksanaan kontruksi pada pertemuan natara kolom dengan dinding (nah yang ini adalah posting yang and abaca sekarang)
BIAYA PLESTERAN DINDING
Kebutuhan | Indeks | Satuan | Harga Satuan | Jumlah | |
(1) | (2) | (3) | (4) | (5)=(2)*(4) | |
Bahan | PC (semen) | 3,000 | Kg | Rp 1.050 | Rp 3.150 |
KP (Kapur padam) | 0,005 | m³ | Rp 120.000 | Rp 600 | |
PP(Pasir Pasang) | 0,020 | m³ | Rp 120.000 | Rp 2.400 | |
Tenaga kerja | Pekerja | 0,360 | oh | Rp 42.500 | Rp 15.300 |
Tukang batu | 0,120 | oh | Rp 52.500 | Rp 6.300 | |
Kepala tukang | 0,012 | oh | Rp 55.000 | Rp 660 | |
Mandor | 0,018 | oh | Rp 60.000 | Rp 1.080 | |
Sumber SNI 2837:2008 | Harga satuan | Rp 29.490 |
Kebutuhan | Indeks | Satuan | Harga | Jumlah | |
(1) | (2) | (3) | (4) | (5)=(2)*(4) | |
Bahan | Semen | 3,25 | Kg | Rp 1.050 | Rp 3.413 |
Tenaga kerja | Pekerja | 0,2 | Oh | Rp 42.500 | Rp 8.500 |
Tukang batu | 0,1 | Oh | Rp 52.500 | Rp 5.250 | |
Kepala tukang | 0,01 | Oh | Rp 55.000 | Rp 550 | |
Mandor | 0,01 | Oh | Rp 60.000 | Rp 600 | |
Sumber SNI 2837:2008 | Harga satuan | Rp 18.313 |
Harga satuan yang ada didaerah anda bisa saja lebih rendah dari yang tercantum di Gambar 48.1 dan di gambar 48.2
Pembaca sekalian, perhatian kita masih tetap pada Gambar 48.1 dan 48.2, dari table tersebut dapat kita peroleh beberapa informasi yang berkaitan dengan kedua pekerjaan tersebut :
- Perhitungan bahan pekerjaan
- Dalam melakukan pekerjaan 1m2 ketebalan 15mm dengan perbandingan campuran bahan 1PC:2KP:8PP membutuhkan bahan 3 Kg semen, 0.005m3 Kapur pasang, 0.02 m3 pasir pasang. Nah kalau sudah tahu kebutuhan bahan tiap m2 sekarang tinggal hitung saja berapa luas pekerjan pelesteran rumah anda dan tinggal dikalikan saja.
- Trus bagaimana dengan kebutuhan bahan untuk pekerjaan acian, saya yakin anda sudah mengetahuinya kalau mengaci dihutuhkan bahan 3.25 Kg semen.
- Perhitungan tanaga pekerjaan
Coba perhatikan perhitungan di bawah ini
Kebutuhan | Indeks | Satuan | hitungan | Produksi Tiap Hari |
(1) | (2) | (3) | (4) | (5)=1/(2) |
Tukang batu | 0,120 | oh | 1 / 0,120 | 8,33 |
Sumber SNI 2837:2008 |
- Dari tabel tadi didapatkan hasil bahwa produktifitas tukang plester dinding sesuai SNI adalah 8.33m2 dalam satu hari bekerja, di mana sesuai dengan SNI bahwa jam bekerja efektif tukang dalam 1 hari adalah 5jam. NaH sekarang masih tertingal pertanyan lha kenapa kok pekerja, kepala tukang dan mandor tidak dihitung?ya jawabanya dalam pekerjaan pelester dinding pekerjaan utama dilakukan oleh tukang sedangkan yang lain sifatnya penunjang, tentu saja pekerjaan tersebut tidak akan terwujud jika tanpa pembantu pekerjaan atau pekerja.
- KOMPOSISI PEKERJA DALAM PELAKSANAAN PEKERJAAN PELESTERAN
Kebutuhan | Indeks | Satuan | Hitungan | Produksi tiap hari |
(1) | (2) | (3) | (4) | (5)=1/(2) |
Tukang batu | 0,1 | Oh | 1/0.1 | 10 |
Sumber SNI 2837:2008 |
Kesimpulan dari tabel tersebut adalah :
- Dalam melakukan pekerjaan acian tiap meter diperlukan bahan semen 3.25 kg.
- Dalam sehari seorang tukang batu bisa membuat 10 m’
- Perbandingan antara tukang dan tenaga adalah 2:1
- Nah kalau cara menghitungnya anda pasti sudah bisa, tinggal nyonteksaja kan.